Repair works at Collingwood Town Hall

13 March 2017

Repair works at Collingwood Town Hall

Works are underway to repair the roof at Collingwood Town Hall.

The works will involve replacing gutters and downpipes and fitting the roof with new slate tiles to ensure it is good condition and water tight for the next 100+ years.

The work has been approved by Heritage Victoria and the clock will continue to work throughout the project.

From Monday 13 March, scaffolding will be installed on the north side of Collingwood Town Hall. This is likely to be in place for about six weeks.  

Works and scaffolding will then relocate to the south side of the building (the Stanton Street side), followed by the north-west corner and then to clock tower, which will involve installing scaffolding on the façade of Collingwood Town Hall. 

The full program of works is expected to be complete in June 2017.

 


 